Rapid restoration of critical wastewater infrastructure
Renovation of the wastewater pumping station in Chernihiv
To stabilize urban wastewater disposal in Chernihiv, the Deutsche Gesellschaft für Internationale Zusammenarbeit commissioned Julius Berger International GmbH with the planning and supervision of the rehabilitation of a severely damaged wastewater pumping station. Before its destruction, the facility was responsible for around 25 percent of the municipal wastewater, making it crucial for environmental and public health protection. Massive damage to the electrical infrastructure caused by military actions made rapid restoration urgently necessary. The extremely challenging security situation also required that the entire project be managed completely remotely.
Julius Berger International developed a modular, container-based interim solution that enabled a swift recommissioning while also preparing for later integration into a permanent infrastructure. The technical equipment includes a compact transformer station, high-performance transformers, an emergency power supply, and frequency-controlled pump management for energy-efficient and reliable plant operation. All electrical components are housed in certified containers, providing protected operating spaces. An underground cable duct and pipe bank system ensures safe, low-maintenance, and durable power distribution.
As Lead Designer Plus, Julius Berger International was responsible for planning, tendering, construction supervision, and reporting. Through structured project organization, technical expertise, and close coordination with local partners, a timely and cost-efficient solution was realized that sustainably stabilizes wastewater disposal, reduces environmental impact, and makes a significant contribution to the urban resilience of the city.
Design and Engineering
- Approval planning
- Concept studies and design concepts
- Execution and detail planning
- Schematic design and design development
Construction management
- Tender documents and specifications
- Award of contract
- Construction monitoring
5D BIM
Project management
- Coordination between clients and authorities
Construction-related services
- Scheduling
- Construction process planning
Consulting
- Technical Consulting
Integrated planning. Sustainable engineering. A secure future.
Sustainable, efficient and future-ready engineering projects. Learn how our team works together with our strong network to help you overcome the challenges on your journey towards a carbon-neutral future.
Sustainable design and engineering- Aenergen
- Aldi
- Albert Speer + Partner
- Amazon
- Apleona
- Automotive Cells Company
- Aws
- Bad Neuenahr-Ahrweiler
- BASF
- Bayer
- Bauverein AG Darmstadt
- Bilfinger
- Boll und Partner
- Bollinger und Grohmann
- BSG Heidelberg
- Clifton Scannell Emerson Associates
- Dechant
- Deutsche Bahn
- Dreßler Bau
- Ebwo
- Eiffage
- Etco
- Eurovia
- Ewe Go
- Exyte
- Faber Bau
- Four
- Frasers Group
- GIZ
- Grebner Ingenieure
- GWW Wiesbaden
- Heberger
- ILF
- Hochtief
- Implenia
- Ingenieurgruppe Bauen
- Keller Grundbau
- Konstruktionsgruppe Bauen
- Lysander
- Max Bögl
- Mewa
- NDC-Garbe
- OFB Projektentwicklung
- Palm Hills Developments
- Parx
- Peri
- Royal Haskoning
- SEG Wiesbaden
- Sweco
- The Flag
- TransnetBW
- Schnorpfeil
- Vacuumschmelze
- Van Oord
- Verbandsgemeinde Altenahr
- Verbandsgemeinde Niederolm
- Wayss & Freytag
- WTM Engineers
- Wörner Traxler Richter
- Züblin